I have this DAX code to show how many minutes a process ran:
However, it's showing anything less than 1 minute, but more than 1 second as 1 minute. If I have the minimum time on 1, it should not show any rows less than 1 minute.
For example, these rows are returned with the slicer above applied, but shouldn't.
Please help!
I figured it out. Changed my DAX to:
Process Time Minutes = DATEDIFF(META[PROCESS_START_TIME], META[PROCESS_END_TIME], SECOND) / 60
3 Replies
- J918Frequent Visitor
I figured it out. Changed my DAX to:
Process Time Minutes = DATEDIFF(META[PROCESS_START_TIME], META[PROCESS_END_TIME], SECOND) / 60 - mark_endicottSuper User
J918 - The slicer is turning the correct values for what you are doing. In order for this to work, you will need to turn your column into an integer for minutes, try:
DATEDIFF(META[PROCESS_START_TIME], META[PROCESS_END_TIME], SECOND) / 60If this works, please accept it as a solution.
- AnonymousNot applicable
We are really glad to know that the problem has been solved. We're also glad that you've shared your solution in the community, it's very helpful.
Please consider accepting your post as a solution to help other members find solutions faster.
Certainly, if there is anything else we can do for you, please do not hesitate to contact us.
Best Regards,
Leroy Lu