Date status column

Dear Community, I am looking to create a column which indicates the status of each task which covers all eventualites. I am using four date columns, Start Date, Finish Date, Actual Start & Actual Fi...
  • DimaMD's avatar
    4 years ago

    JoeHazelton I tried to simulate the example data, look maybe it will lead you to the right idea in solving your problem

    measure = 
    SWITCH( 
        TRUE(),
        [Start Date] > TODAY(), "Planned",
        AND([Start Date], [Finish Date]) && AND([Actual Start], [Actual Finish]) <> BLANK(), "Complete",
        AND([Start Date] <= TODAY(), [Actual Start] = BLANK()),  "Late Starting", 
        "Late Finishing"
          )