Good afternoon, I was writing to you because I want to see the sum of times, in time format, and not the earliest as it is currently displayed. In advance, thank you very much for everythi...
amitchandak
4 years agoSuper User
pinolss , You need to convert to second , add and again change at time display .
refer if these blogs can help
https://radacad.com/calculate-duration-in-days-hours-minutes-and-seconds-dynamically-in-power-bi-using-dax
https://social.technet.microsoft.com/wiki/contents/articles/33644.powerbi-aggregating-durationtime-in-dax.aspx