Multi level hierarchy in Gantt chart by microsoft corporation

Hello everyone,

I have a requirement of three levels of hierarchy in Gantt chart by microsoft corporation. Like for example Function-Department in first level, worflows in second level, and sub workflows in third level . I can just see parent task as of now. Is there any workaround for this?

  • The Microsoft Gantt visual does not support more than 2 hierarchy levels. Other alternative for you could be:

     

    1) Use a Matrix + Gantt workaround

    • Use a Matrix visual for:

      • Department

      • Workflow

      • Sub-workflow

    • Use conditional formatting or bars (via measures) to simulate timelines

     

    2) Use a custom Gantt visual (recommended if hierarchy is critical)

    Some custom visuals support deeper hierarchies, for example:

    • xViz Gantt

    • MAQ Gantt

    • Other AppSource Gantt visuals

5 Replies

  • Hello everyone,

     

    • I have a requirement of three levels of hierarchy in Gantt chart by microsoft corporation. Like for example Function-Department in first level, worflows in second level, and sub workflows in third level . I can just see parent, task as of now. Is there any workaround for this?
    • cengizhanarslan's avatar
      cengizhanarslan
      Icon for Super User rankSuper User

      The Microsoft Gantt visual does not support more than 2 hierarchy levels. Other alternative for you could be:

       

      1) Use a Matrix + Gantt workaround

      • Use a Matrix visual for:

        • Department

        • Workflow

        • Sub-workflow

      • Use conditional formatting or bars (via measures) to simulate timelines

       

      2) Use a custom Gantt visual (recommended if hierarchy is critical)

      Some custom visuals support deeper hierarchies, for example:

      • xViz Gantt

      • MAQ Gantt

      • Other AppSource Gantt visuals

  • The Microsoft Gantt visual does not support more than 2 hierarchy levels. Other alternative for you could be:

     

    1) Use a Matrix + Gantt workaround

    • Use a Matrix visual for:

      • Department

      • Workflow

      • Sub-workflow

    • Use conditional formatting or bars (via measures) to simulate timelines

     

    2) Use a custom Gantt visual (recommended if hierarchy is critical)

    Some custom visuals support deeper hierarchies, for example:

    • xViz Gantt

    • MAQ Gantt

    • Other AppSource Gantt visuals

  • Hi Siddu8867 ,

    Could you please let us know if your issue has been resolved, or if you need any additional information from us.  We’ll be happy to help.

     