End Date incorrect on Gantt chart 3.0.12.0
In 'Transform data' my dates are Start Date (01/25/2024 13:00 or 1:00PM) and End date (01/26/24 11:00 or 11:00AM)
WV End Date Actual is a hard date written in the source while the All End date is calculating within PowerBI the start date plus the duration. Both are getting the same results of (01/26/24 11:00 or 11:00AM)
however, in the Gantt chart the End Date is (01/26/2024 13:00 or 1:00PM)
This is how I have the Visualizations sets up
How do I get the chart to provide the correct end date?